Safe
We looked for evidence that staff protected people from avoidable harm and made sure care was delivered from environments that were clean and well maintained. At our last assessment, we rated this key question as good. At this assessment, the rating remains the same.
This service scored 63 (out of 100) for this area. Find out what we look at when we assess this area and How we calculate these scores.
Learning culture
We did not look at Learning culture during this assessment. The score for this quality statement is based on the previous rating for Safe.
Safe systems, pathways and transitions
We did not look at Safe systems, pathways and transitions during this assessment. The score for this quality statement is based on the previous rating for Safe.
Safeguarding
We did not look at Safeguarding during this assessment. The score for this quality statement is based on the previous rating for Safe.
Involving people to manage risks
We did not look at Involving people to manage risks during this assessment. The score for this quality statement is based on the previous rating for Safe.
Safe environments
The service did not always detect and control potential risks in the care environment. They did not always make sure equipment, facilities and technology supported the delivery of safe care.
The service had not always effectively addressed risks relating to fire safety and health and safety. Although fire risk assessments had been undertaken, actions identified through assessments completed in 2022 and 2023 had not all been completed. For example, a recommendation to upgrade the fire detection system from a domestic to a commercial system had not been implemented at the time of our assessment. Whilst the service advised weekly fire alarm bell tests were being completed, records of these checks were not available during our visit. However, during our onsite visit, we did not identify any immediate fire safety or health and safety risks within the premises. Following our onsite visit, the service arranged for an external company to complete a new fire risk assessment the following week. The service also confirmed it had introduced a system to record weekly fire alarm bell tests and provided assurance that these checks would continue to be completed.
Whilst Legionella temperature checks were undertaken monthly, annual Legionella testing had not been completed since 2023, which was not in line with the service's own protocol. In addition, the service was unable to provide a Legionella risk assessment. However, a member of staff had recently been appointed as the Legionella lead, and arrangements had already been made for an annual Legionella review, a new risk assessment and the overdue annual Legionella testing to be completed by an appropriate external provider in September 2026.
The service’s own asbestos report confirmed that both the main and branch sites had low-risk asbestos-containing materials; however, the service did not have an asbestos management plan to demonstrate how these risks would be monitored and managed. Following our onsite visit, the service confirmed it had added the asbestos risk within its premises to a newly created risk register to support ongoing monitoring and management of the identified risk. We also observed that some chairs within the waiting area had damaged upholstery, which may impact effective cleaning. Following our visit, the service confirmed replacement of the affected chairs was being progressed and that the issue had been formally recorded to support ongoing monitoring.
Safe and effective staffing
The service did not always make sure there were enough qualified, skilled and experienced staff. They did not always make sure staff received effective support, supervision and development. They did not always work together well to provide safe care that met people’s individual needs.
Whilst the service had a training policy and training matrix in place, the matrix did not fully reflect all training identified as mandatory within the service's own policy. During our review of the matrix, we identified gaps in training records and noted training requirements had not always been appropriately aligned to staff roles. For example, a clinician was not up to date with 14 of the 17 training modules identified as mandatory for their role. It was also noted clinical staff were required to complete ‘Level 2 infection prevention and control’ training in accordance with the service's policy; however, this had not been configured on the training platform used by the service, and some clinical staff had only completed ‘Level 1’. As a result, although some staff had completed training, it was not at the level required for their role in accordance with the service's policy. From speaking with staff during our assessment, we did not identify any knowledge gaps despite the training issues identified.
Following our onsite visit, leaders took action to address the concerns identified. This included reviewing and revising the mandatory training requirements to ensure these were aligned to individual staff roles. Staff who required training at a higher level were informed to complete the appropriate modules within a specific timeframe. The service also put arrangements in place to support clinicians to complete their outstanding training, by providing protected time for training completion.
All staff received annual appraisals, and these were documented. Non-medical prescribers working at the service were employed by another practice within the Primary Care Network (PCN). We were told by leaders that clinical supervision of those clinical staff members was undertaken by the lead GP from their employing practice, with arrangements set out within the relevant supervision policy.
Recruitment records were not always maintained in line with national legislation. We reviewed a sample of 4 staff files, and, for 1 clinician, the service was unable to provide evidence of professional registration checks or qualifications. Following our onsite visit, the service confirmed it had undertaken a professional registration check to verify the clinician was appropriately registered with a professional body and had requested evidence of qualifications from the individual concerned. We did not identify similar concerns in the remaining 3 staff files we reviewed.
The service was not routinely obtaining or recording information relating to staff physical or mental health in line with national guidance, nor were Display Screen Equipment (DSE) assessments routinely completed for staff. However, leaders were able to demonstrate reasonable adjustments were made where required, including the provision of standing desks, although these arrangements had not always been formally documented. Following our onsite visit, the service confirmed that DSE assessments would be undertaken for all staff and planned for completion by October 2026.
When reviewing Disclosure and Barring Service (DBS) records, we noted some staff had commenced employment before their DBS checks had been completed and had done so without an appropriate risk assessment to assure the service of their suitability to work with vulnerable people. However, we did not identify any concerns regarding the suitability of staff, and most staff had worked at the service for a prolonged period of time. Following our onsite visit, the service provided a risk assessment template to be used where staff commence employment before a DBS check has been returned. The template set out specific control measures for both clinical and non-clinical staff, including restrictions on unsupervised contact with people.
Infection prevention and control
The service did not always assess or manage the risk of infection. They did not always detect and control the risk of it spreading or share concerns with appropriate agencies promptly.
Whilst the service had an infection prevention and control (IPC) policy at the time of our onsite visit, information within the policy was not up to date and did not contain all relevant information for staff to be aware of, such as who the service’s IPC lead was.
Hand hygiene audits were completed routinely for both clinical and non-clinical staff. Spillage kits were available and were within their expiry dates. Clinical staff were responsible for using these when required, although reception staff could also provide support if necessary. However, staff files reviewed as part of this assessment indicated immunisation records had not been obtained or recorded for all non-clinical staff. Given some such staff may be involved in responding to incidents involving blood or bodily fluid spillages, the service could not demonstrate all staff had received immunisations appropriate to the requirements of their role. The service had identified this issue prior to our assessment and was already taking steps to ensure all staff had evidence of the immunisations required for their work.
The Control of Substances Hazardous to Health (COSHH) cupboard did not have appropriate signage in place; however, signage was ordered for next-day delivery during our onsite visit. Not all cleaning products in use had the corresponding Material Safety Data Sheets (MSDS) available, and COSHH risk assessments were not available for all products used at the service. This is not in line with national guidance. In addition, the COSHH cupboard was not secured to prevent unauthorised access. In response to us identifying this, a padlock was ordered during the onsite visit.
During our onsite visit, the service was observed to be clean, tidy and well-maintained. However, cleaning schedules completed by the service's employed cleaner did not provide full assurance of adherence to national cleaning standards. Whilst records showed that touchpoints and rooms had been cleaned daily, itemised cleaning records were not available to provide assurance regarding what had been cleaned and when, in line with the services overall cleaning schedule. However, carpet cleaning schedules were available and demonstrated that carpet cleaning was undertaken 6 monthly.
Following our onsite visit, the service introduced itemised cleaning logs for each room within the service, to be completed daily.
Medicines optimisation
The service did not always make sure that medicines were stored securely or that documentation to administer certain medicines were completed in line with national recommendations. However, the service made sure care and treatment met people’s needs, capacities and preferences. They involved people in planning and ensured people receive evidence-based, clinically effective and safe prescribing.
During our onsite visit, we noted a sample of Patient Group Directions (PGDs) had not been completed in line with national legislation. PGDs are written instructions that allow specified medicines to be supplied or administered to groups of people without the need for an individual prescription. We reviewed all the PGDs and noted unused authorisation rows had not always been scored through once the document had been completed and authorised. We raised this with the service, who confirmed it would review these to ensure they were completed correctly.
Emergency medicines were not stored directly with the emergency equipment and were instead kept in a locked cupboard that was only accessible to clinical staff, which was not in line with national recommendations. In addition, the medicines were not stored in a tamper-evident manner, as per national recommendations. On reviewing the service's emergency medicines, we also noted not all emergency medicines recommended for GP practices were available within the emergency medicines kit. The service had also not completed a documented risk assessment relating to the emergency equipment and medicines held on site, including the rationale for medicines not held on site or the clinical mitigation in place to manage any associated risks.
Following our onsite visit, the service took action to address the concerns identified. Leaders completed a risk assessment relating to the emergency medicines held on site, including the rationale for medicines not stocked by the service and the clinical mitigation in place to manage any associated risks. The service also ensured emergency medicines and emergency equipment were stored together in an accessible location to support a timely response in an emergency. In addition, emergency medicines were stored in a tamper-evident manner, providing greater assurance that stock remained secure and had not been accessed or altered. The emergency medicines inventory was also reviewed and updated to accurately reflect the medicines held by the service.
Whilst vaccine fridges were located within a treatment room and were kept locked in line with national guidance, the keys remained in the fridge locks, meaning they could potentially be accessed by unauthorised persons, as the treatment room was observed to be unlocked during our onsite visit. Following our visit, the service confirmed the fridge keys had been removed and were now stored securely in a key safe. The vaccine fridges were otherwise appropriately monitored, with minimum and maximum temperatures recorded daily and no concerns were identified from the records reviewed.
However, as part of our assessment, we carried out remote clinical searches and reviewed samples of care records within the service's clinical system. These demonstrated that people received appropriate monitoring in line with national guidance and that medicines were managed safely across the service. Staff involved people in reviews of their medicines and supported them to manage their medicines safely. Medication and long-term condition reviews were detailed, person-centred and completed in a structured way. Reviews considered the individual needs and best interests of each person.
Staff followed protocols to ensure medicines were prescribed safely and that people received the reviews and monitoring required for their prescribed medicines. Clinical searches demonstrated effective medicines management, including appropriate monitoring for people prescribed high-risk medicines and disease-modifying antirheumatic drugs (DMARDs), in line with national guidance. For example, of the 28 people prescribed medicines such as methotrexate, all had received blood test monitoring in line with national guidance.
Safety alerts and medicine recalls were managed safely. The service worked closely with the local primary care network (PCN) pharmacist to ensure relevant alerts were reviewed, actioned and communicated appropriately.