On this page

Safe

Requires improvement

6 November 2026

Safe – this means we looked for evidence that people were protected from abuse and avoidable harm. At our last assessment we rated this key question good. At this assessment the rating has changed to requires improvement. This meant some aspects of the service were not always safe and there was limited assurance about safety. There was an increased risk that people could be harmed.

The service was in breach of legal regulation in relation to safeguarding at the service. We found people had not always had Deprivation of Liberty Safeguard (DoLS) applications made as required.
 

This service scored 59 (out of 100) for this area. Find out what we look at when we assess this area and How we calculate these scores.

Learning culture

Score: 2

Staff did not always fully investigate or record safety events. Lessons were not always learnt to continually identify and embed good practice. However, the manager had a positive culture of safety based on openness and honesty.

Staff completed accident and incident reports, which the manager reviewed. Reports were not always fully completed, for example details of how the accident could have been prevented were not always recorded, and it was not always clear what actions had been taken following the manager’s review. Accidents and incidents were not routinely monitored to identify any themes and trends.
The manager shared an updated incident form they planned to use moving forward to ensure any actions taken such as updating risk assessments were clearly recorded and any lessons learnt were shared.
The manager and staff team had recently agreed an approach to follow to support 1 person who may experience anxiety. Staff told us they discussed learning relating to people’s care. One staff member said, “We sit and talk around the table, anything we need to change gets addressed and shared in the communication book.”
 

Safe systems, pathways and transitions

Score: 3

The manager worked with people and healthcare partners to establish and maintain safe systems of care, in which safety was managed or monitored. They made sure there was continuity of care, including when people moved between different services.

Staff supported people to attend hospital appointments and admissions. People had a hospital passport which shared important information with health professionals.
The service made referrals for people when they required additional support from external health professionals, such as physiotherapists or occupational therapists.
People were supported with their transition to living at the home. People were able to visit and spend time at the service before they moved in permanently. Staff confirmed people’s care plans were shared with them in advance to support them to get to know people.
A health and social care professional shared their experience of a person’s move into the home and said, “The team completed a comprehensive handover with the previous care provider, ensuring that important information such as the person’s medication routine, was shared and understood.”
 

Safeguarding

Score: 2

The manager worked with people and healthcare partners to understand what being safe meant to them. Although we found some improvements were needed to ensure people were not deprived of their liberty without the appropriate legal framework being in place.

People can only be deprived of their liberty to receive care and treatment with appropriate legal authority. In care homes this can be done through a procedure called the Deprivation of Liberty Safeguards (DoLS), which is part of the Mental Capacity Act 2005 (MCA). We checked whether the service was working within the principles of the MCA and how they managed DoLS within the service. 2 people had a current DoLS authorisation and conditions attached to these authorisations had been completed. However, the manager had not submitted DoLS applications for 5 people who they had assessed in line with the Mental Capacity Act (MCA) to lack capacity to consent to their care arrangements, including not being free to leave, and any restrictions they were subject to. This meant people were being deprived of their liberty without the necessary legal framework being in place. We also found the manager had not notified CQC of outcomes of DoLS applications as required. We did not find any people were communicating they were not happy with their living arrangements or wished to leave the service.


The manager reported any safeguarding concerns appropriately and recorded and monitored any required actions. People and their relatives told us people were safe. People and staff had information available to them to enable them to raise a concern. Staff had completed safeguarding training and told us they understood their responsibilities in relation to safeguarding. One staff member said, “It is our role to keep the residents free from harm, to have a good quality of life and to make sure there is no abuse.”

Involving people to manage risks

Score: 2

The manager did not always work well with people to understand and manage risks. However, staff provided care to meet people’s needs that was safe, supportive and enabled people to do the things that mattered to them.

The manager completed risk assessments for people. However, not all risks to people had been sufficiently assessed. For example, where people had health conditions such as diabetes, care plans contained limited information for staff on the support people needed to safely manage their condition. One person had some restrictions imposed to manage risks which could negatively affect their health, however this restriction and the associated risks were not documented in a risk assessment. Another person was at risk of falling when using the stairs, their risk assessment had not recorded all risks or safety measures which had been identified to mitigate risks.
Where people were at risk of choking and required a modified diet, speech and language therapist (SALT) guidelines were clearly documented in people’s care plans and staff had a good understanding of how meals needed to be prepared to manage the choking risk. However, 1 person chose to eat foods not in accordance with their SALT guidelines. Their eating and drinking risk assessment did not show how the choking risk associated with this had been assessed or managed.
The provider had not assessed the associated fire risks for people who were prescribed emollient creams.
Staff knew people well and the support people needed to manage areas of risk. However, some of the arrangements staff followed to mitigate risk were not recorded in people’s care plans or risk assessments.
Where people experienced behaviours of distress, they had personalised care plans which recorded their needs in this area and approaches to support the person.
 

Safe environments

Score: 2

The manager did not always detect and control potential risks in the care environment. They did not always make sure equipment, facilities and technology supported the delivery of safe care.

Although the premises was largely well maintained there were some areas of risk which needed to be addressed to ensure it was always a safe environment.
Staff had all completed fire training. However, they had not all taken part in a recent fire drill and not all staff were clear on the actions they should take to support people in the event of a fire. Some fire evacuation procedures displayed within the home had different instructions.
Personal Emergency Evacuation Plans (PEEPs) and individual fire risk assessments assessed the level of support people required in the event of a fire. However, 1 person’s PEEP and fire risk assessment did not provide clear information on the actions staff should take to keep them safe. We shared our findings with the manager who shared the updated PEEP with us. They told us staff fire drill practice had been completed or scheduled, and the fire risk assessment would also be reviewed.
The manager completed health and safety audits. However, the audits contained limited detail, some areas of the audits had not been completed for several months and had not identified the concerns we found.
Regular safety checks of the environment including fire, water and electricity were being completed.
 

Safe and effective staffing

Score: 3

The manager made sure there were enough qualified, skilled and experienced staff. They worked together well to provide safe care that met people’s individual needs. They made sure staff received effective support and development. However, staff did not receive regular supervision.

Staff received training to support people’s needs, and the manager monitored training compliance. Staff had completed specific training to support people with a learning disability and autistic people.

People told us staff treated them well and they felt safe. Relatives told us there were enough staff and people were well supported. A health and social care professional said, “There appears to be a high staff presence, and residents appear to have support available at all times.”

Staff completed appropriate recruitment checks to ensure they were safe to provide care and support. However, the manager had not always explored gaps in staff employment histories or renewed Disclosure and Barring Service (DBS) checks for long-standing staff. The manager planned to enrol staff on the DBS update service.

Staff did not receive regular supervision, appraisals or probationary reviews as required by the provider’s policy. This limited opportunities to formally assess staff understanding of training and support their development. However, staff told us they felt well supported by the manager. One staff member said, “I can ask for a private conversation, the manager is very approachable.”
 

Infection prevention and control

Score: 3

The manager assessed and managed the risk of infection. They detected and controlled the risk of it spreading and shared concerns with appropriate agencies promptly.
Care plans guided staff on supporting people with their personal hygiene. Staff provided this support sensitively and discreetly. The service was clean and tidy, staff completed daily cleaning schedules and used personal protective equipment appropriately.
A health professional told us, “I have seen staff providing personal care respectfully, assisting residents with their hygiene needs and maintaining clean and hygienic surroundings.”
 

Medicines optimisation

Score: 2

The manager did not always make sure that medicines and treatments were safe and met people’s needs, capacities and preferences. However, staff involved people in planning, including when changes happened.
We found gaps in 1 person’s topical medicine records, so we could not be assured staff always administered the medicine as prescribed. Staff did not check medicines records daily to identify and address gaps promptly. Instead, a senior staff member checked records during monthly audits, which meant the identification of potential errors might be delayed. We found no evidence people had been harmed. The manager had also not completed staff annual medicines competency checks.

Information for staff about how to support people to take their medicines was detailed and included people’s preferences. When people were being supported to take their prescribed medicines, staff followed people’s preferences and gained their consent before administration. Clear protocols were in place for administering as required medicines for people who experienced behaviours of distress.